WATER MAIN PROJECT UPDATES

EAST Section: Herring River Bridge to South Street (largest section)

WEST Section:  Herring River Bridge to Divisiont Street (smaller section)

 

Route 28 Water Main Projects Update:  Week of November 16, 2026

Route 28 East: Dig It Construction began work on the Route 28 East watermain replacement project on Monday, November 16, at the intersection of Route 28 and Lothrop Ave. Watermain installation will progress east toward Harwich Port.

Route 28 West: CC Construction has no watermain work planned for the next two weeks. During that time, CC Construction will be on site installing new drainage in coordination with the MassDOT road reconstruction project. This work is expected between the Herring River and Riverside Drive.

Detour Notice: Vehicle traffic for both projects will be detoured via Lower County Road. Motorists should watch for flaggers and signs and allow extra travel time. Project look-aheads and detour maps are included in the Select Board packet and are posted on the Town’s website.

Route 28 Water Main Projects Update:  Week of November 2nd, 2026

West Project: Beginning the week of November 2, CC Construction will install insertion valves at various locations along Route 28 between Riverside Drive and Division Street. No water main shutdowns are planned, and no interruptions to water service are expected. Once the insertion valves are complete, CC Construction plans to begin installing the low-pressure sewer main, starting at Division Street and progressing east.

East Project: On Monday, November 2, Dig IT Construction will complete two 16-inch insertion valves on Miles Street and Earle Road. Throughout the remainder of the week, Dig IT will be receiving pipe deliveries, preparing the laydown area, and mobilizing materials and equipment in advance of mainline work. Mainline pipe installation is scheduled to begin the following week in the area of Lothrop Avenue and Route 28, progressing east toward Harwich Port.

Route 28 West Project Update 10/26/26

The project reached a major milestone today: CC Construction has completed the new watermain installation at the intersection of Route 28 and Division Street, wrapping up the mainline construction.

Work still remaining on the water system includes cross street tie-ins, hydrant installations, water and fire service connections, and pressure testing and disinfection of the new main.

Upcoming work:

  • Hydrant installation: CC is now moving on to hydrant installation, working from the Dennis town line toward the Herring River.
  • Insertion valve: CC will install an insertion valve near the Herring River so the new main can be filled and tested. A firm date is still pending, but installation is expected this week or next.
  • Low pressure sewer: CC plans to begin the low pressure sewer installation within the next one to two weeks. Their schedule has been in flux, so a firm start date is not yet available; updates will follow as it's confirmed.

Route 28 East Project Update

Dig It Construction has no work planned for the current week. Next week, they anticipate installing two (2) 16-inch insertion valves in the area of Miles Street and Route 28.

Dig It is hoping to begin the mainline installation soon, but a firm start date has not yet been set. MassDOT has advised that it will not authorize Dig It to work on Route 28 until additional information is provided on the Horizontal Directional Drill (HDD) beneath the Herring River, even though the HDD work is separate and distinct from the mainline installation in the roadway.

Dig It has submitted a request to MassDOT to begin the mainline installation while the HDD information is being prepared. No response has been received as of today; updates will follow once MassDOT responds and a start date is confirmed.


Route 28 Water Main Projects Update: Week of 10/19/26
Beginning the week of October 19, CC Construction will continue the Route 28 West Water Main Project at the intersection of Route 28 and Division Street, completing a 12-inch water main tie-in and extending the water main along Division Street near the intersection, then moving on to fire hydrant installation at various locations along Route 28 between Riverside Drive and Division Street. CC Construction has submitted a detour plan for the Division Street work that is currently under MassDOT review; if it is not approved, traffic on Division Street will be reduced to one alternating lane, managed by police details and/or flaggers, and once hydrant installation begins, Route 28 traffic between Riverside Drive and Division Street will be detoured via Lower County Road.
On the Route 28 East Water Main Project, Dig It Construction will be excavating on Monday, October 19, at Sisson Road and at Doane Road to install two insertion valves, with lane shifts and traffic control expected near both work areas that day and no further work planned for the rest of the week (October 20–23). No water main shutdowns or service interruptions are expected on either project, and access for residents and businesses along the West project route will be maintained and coordinated by the onsite detail officer and/or flagger. Motorists should allow extra travel time, follow posted signage and traffic control personnel, and use alternate routes when possible.

9/30/26 Two-Week Lookahead

Harwich Rt. 28 (East) – Water Main

1-Week Look Ahead (October 5 – October 9) - Route 28 (from Lothrop Avenue to South Street)

2-Week Look Ahead (October 12 – October 16)

Notice to Residents

Construction activities will be performed Monday through Friday. During the upcoming two week period, work along Route 28 will primarily consist of preliminary construction activities and no excavation is anticipated.

There will be no road closure on Route 28 during this work. Traffic will be maintained using a one lane alternating traffic management plan affecting the eastbound lane within the active work area. Police and Traffic Control Officers, along with appropriate traffic control signage, will be in place to assist motorists safely through the work zone.

Since no excavation is planned during this two week period, residents and businesses will maintain full access to their driveways and parking lot entrances. School transportation, including normal pickup and drop off locations, is not anticipated to be affected by the planned work.

Please note that this is a projected schedule and will be adjusted accordingly based on the Contractor's actual progress, weather conditions, material availability, permitting requirements, and other conditions that may affect the work.

Motorists should use caution when traveling through the construction area and allow additional travel time for potential delays associated with alternating traffic. All travel lanes will be reopened at the end of each workday.

9/28/26 Weekly Briefing

Phase 1 (WEST)

CC Construction will continue work on the Route 28 Phase 1 West contract this upcoming week in the area between Murray Lane and Belmont Road. Work will include continued installation of the new 12-inch water main, progressing west toward the Harwich–Dennis town line. No water main shutdowns are planned, and no interruptions to water service are anticipated.

**The contractor has submitted a request to MassDOT to detour traffic around the construction area. As of the preparation of this update, that request remains under review and has not yet been approved.**

Phase 2 (EAST)

The public will also begin to see preconstruction activity associated with the Phase 2 East project. Dig It Construction will perform utility layout and sawcutting along Route 28 between Lothrop Avenue and Harwich Port. Sawcutting is anticipated to begin at Lothrop Avenue and progress east toward Harwich Port.

Route 28 will remain open to vehicular traffic throughout construction. In active work areas, traffic will be reduced to one alternating lane under the direction of police details or Flaggers.

9/21/26 Weekly Briefing

CC Construction began work on Monday, September 14, installing a new 12-inch water main along Route 28 from the Herring River west to just beyond North Road. The contractor also completed additional pavement sawcutting between Riverside Drive and Belmont Road in preparation for the next section of installation.

During the week of September 21, CC Construction will continue installing the new water main between Riverside Drive and Belmont Road, progressing from east to west. No water main shutdowns are planned, and no interruptions to water service are anticipated.

**The contractor has submitted a request to MassDOT to detour tra????ic around the construction area. As of the preparation of this update, that request remains under review and has not yet been approved.**

9/14/26 Weekly Briefing 

CC Construction is planning to begin work on Monday, September 14. I have put together the attached graphic showing the area where CC anticipates working during the first week of construction. 

The attached three-week look-ahead schedule forecasts approximately 200' of water main installed per day. Before publishing the broader schedule publicly, I would like to see how far they get during the first week and whether 200'/day is realistic.

The work will consist primarily of installing the new water main adjacent to the existing main. No water main shutdowns or work on the existing water infrastructure is currently planned, so there should not be any significant impacts to the water system or customer service.

Vibratory compaction near the existing water main could potentially disturb iron or manganese particles built up on the inside of the pipe. Although no widespread impacts are anticipated, this could result in temporary discoloration or particles collecting in a customer’s faucet aerator.